REC delays Moses Lake expansion start-up

OSLO, Feb 9 (Reuters) – Norwegian solar industry group Renewable Energy Corp. (REC) on Monday announced a delay in the expansion of its polysilicon production plant in Moses Lake, Washington, now expected to start up in late March.

Shares in REC initially fell but rebounded, trading up 3.9 percent at 72.10 crowns at 0958 GMT, against a 2.2 percent rise on Oslo’s benchmark index .

REC said last December that the expansion had been delayed to the end of January due to technical problems. On Feb. 2, REC Chief Executive Erik Thorsen told Reuters the Moses Lake start-up was “around the corner”.

“Following the completion of the repairs, a final process of systems checks and start-up procedures will be initiated, before the plant is expected to start commercial production in the second half of March,” REC said in a statement on Monday.

In 2002, REC bought a polysilicon plant in Moses Lake. After the $800 million expansion, the plant will have an annual production capacity of 6,500 tonnes — more than half of REC’s total polysilicon production.

An analyst said its shares rose because the company had clarified the situation.

“There has been uncertainty over whether repairs on the mills were finished. There is more clarity around that now,” analyst Einar Strømstad at First Securities said.

“Secondly…there have been fears of damages also on wafer- cell and module production due to a lack of silicon. It looks like they have managed to buy silicon in the market,” he said.

To read the full story on Reuters.com, click here.

Films of Norway_bunad
Norwegian American Logo

The Norwegian American

Published since May 17, 1889 PO Box 30863 Seattle WA 98113 Tel: (206) 784-4617 • Email: naw@na-weekly.com

You may also like...

%d bloggers like this: